Case study – Refurbishment and partial renewal

Ash and slag transport
Installation location

Wels, Austria

Challenge

Partial modernization of a waste incineration plant that is more than 25 years old

Conveyed material

Ash and slag

Year of construction

2016

Modules

Wet trough chain conveyor, double gate valve, ram slag remover, chutes,
vibrating feeder

Special features

complete dismantling, steel construction and new construction

Case study

Refurbishment and partial renewal

The generation of electricity and heat makes a significant contribution to reducing greenhouse gases and CO2 emissions.

In order to guarantee the productivity of the waste incineration plant in the future, some older plant components have been replaced with new, state-of-the-art conveyor technology. This made a significant contribution to further reducing emissions.